Bomas International Convention Complex: what is being built, what it costs, and why it missed its deadline

A convention centre for 11,000 people at Lang'ata and Magadi roads, built by the Kenya Defence Forces around the clock. It missed its April 2026 target and MPs have questioned its cost. Here is what we know.

The Bomas International Convention Complex under construction

The old Bomas of Kenya cultural centre in Lang'ata is being rebuilt as the Bomas International Convention Complex (BICC), part of the government's plan to make Nairobi a hub for global conferences, beside the new Talanta stadium.

Design image of the Bomas complex with curved buildings among trees
How the finished complex is designed to look.

What is being built

FacilityCapacity
Convention hall5,000 people
Auditorium3,500 seats
Ballroom1,500 guests
Presidential pavilionUp to 30 heads of state
Whole complex11,000 people at once, on more than 32 hectares

The plans also include exhibition halls, a hospitality zone, a landscaped walkway, and a link to the Raila Odinga (Talanta) stadium. Construction is supervised by the Kenya Defence Forces, with work running 24 hours a day.

Construction workers in hard hats gathered at the Bomas site
Work at the site runs day and night, supervised by the KDF.

Cost and deadlines

  • Construction starts.

  • MPs put the cost at about KSh42bn (Ruto has said "almost KSh35bn") and question it, comparing it with cheaper centres such as Kigali's. The project is reported to be about 35% complete.

  • Target missed. The Africa–France summit planned there for May is moved to another venue.

  • The Senate's new completion target; later reports said weather pushed it to 30 September.

Status: we have not seen an official opening announcement. If you have recent photos or news of an opening date, it will be added here. Environmental groups have also raised concerns about plans for parking near Nairobi National Park and moving the animal orphanage.
Aerial views of the Bomas complex under construction
The complex from the air during construction.

Why it matters

  • Conference tourism: big summits bring hotel bookings, jobs and foreign exchange.
  • Public money: at KSh35–42bn, Kenyans deserve a clear cost breakdown and a plan to keep it busy and maintained.

Related: Talanta stadium · Nairobi Railway City arena.

See all projects: Kenya's mega projects tracker.

Watch the video

The New Bomas Complex: KSh35–42bn and Behind Schedule · Subscribe on YouTube

Free, every week

Get one clear explainer in your inbox

New explainers, data and videos, straight from Nairobi. No spam, unsubscribe any time.

Prefer WhatsApp?

Follow the WhatsApp Channel