NSSF Twin Towers' 33-hour pour: why 3,900m³ of concrete went in without stopping
Crews at Nairobi's future tallest building kept the concrete flowing through a night and a day. Here's what they were building, why it couldn't stop, and what 3,900m³ actually looks like.

New site footage from the NSSF Twin Towers in Nairobi shows crews pouring concrete through the night and into the next day. The video's caption says it was a 33-hour pour of about 3,900 cubic metres, and bills it as the largest single concrete pour on a public-sector project in Kenya. The site cameras' timestamps run from late on 20 November into the night of 21 November.

What's a raft foundation?
A tower this tall can't just sit on the ground. The weight of 60 floors has to be spread out. A raft (or mat) foundation is a huge, thick slab of concrete packed with steel bars, laid at the bottom of the excavation, often on top of piles driven deep into the ground. It works like a snowshoe: it spreads the load so the building doesn't sink unevenly.
Why pour it all at once?
- No weak joints. If you stop and let one part harden before adding more, you get a "cold joint", a seam where new concrete meets old. In a foundation carrying a skyscraper, that's a weak spot engineers want to avoid.
- One solid block. A continuous pour lets the whole raft cure as one piece.
- Heat control. Big pours get hot inside as cement reacts. Engineers plan the mix, the order of the pour and the curing to stop cracks.
Read alsoCan a business post your child's photo online without asking? A salon just paid for it3 min read3,900m³ in everyday terms
| Roughly | |
|---|---|
| Weight | About 9,400 tonnes (concrete weighs about 2.4 tonnes per m³) |
| Mixer trucks | About 490 loads of a standard 8m³ truck |
| Pace | About 118m³ an hour, or one truckload every 4 minutes, for 33 hours |
| Swimming pools | More than 1.5 Olympic pools (about 2,500m³ each) |
Our estimates, based on the figures in the site video.
For comparison, an earlier pour for the raft of Tower B was about 1,250m³ in 15 hours. This one is roughly three times bigger.

Where the project stands
- Tower A: 260m, 60 floors, set to be the tallest in East and Central Africa. Tower B: 140m, 35 floors. A 7-storey podium links them.
- Cost: about KSh30 billion, paid for by NSSF, which targets a return of at least 12%.
- Contractor: China Road and Bridge Corporation (CRBC).
- Stage now: excavation is done and the raft foundation is being completed. The towers should start rising above ground next, often at one floor every four to seven days once they get going.
- Completion: expected late 2028 to early 2029.

Why it matters to you
If you pay NSSF, this building is being paid for with your contributions. A well-built foundation is the first step to an asset that has to earn returns for members for decades. It also shows Kenyan crews and suppliers handling the kind of work usually seen on megaprojects abroad. See how much NSSF deducts from your pay.
Frequently asked questions
How much concrete was poured at the NSSF Twin Towers?
Site footage released in November 2026 says about 3,900 cubic metres were poured over 33 hours, billed as Kenya's largest single concrete pour on a public-sector project.
Why is a raft foundation poured continuously?
Stopping lets part of the concrete harden, creating a weaker 'cold joint'. Pouring non-stop makes the foundation one solid block.
When will the NSSF Twin Towers be finished?
Completion is expected between late 2028 and early 2029.
Sources
- Update Shakahola: Paul Mackenzie jailed for 200 years over 191 deaths. What the sentence means
- Update Martha Karua is running for president: who's in the 2027 race so far, and the fight for Mount Kenya
- Update State House wants KSh8.4 billion more: what's in the request, and who decides
- New No water in Kiambu? Why Athi Water switched off 72 million litres a day, and who's affected
- Update Obado jailed for 25 years: the Sharon Otieno murder case, explained