NSSF Twin Towers: East and Central Africa's future tallest building, explained

A 260-metre, 60-storey tower and a 35-storey twin, rising at Uhuru Highway and Kenyatta Avenue. Here is what NSSF is building for KSh30 billion, when it will be done, and why it matters to every worker who pays NSSF.

Two tall glass towers rising over Nairobi
Latest updates to this explainer
  • NSSF rates and the 5% late-payment penalty.
  • Site footage: Tower B raft slab poured in 15 hours.

At the corner of Uhuru Highway and Kenyatta Avenue, on a plot that sat idle for decades, the National Social Security Fund (NSSF) is building what is set to be the tallest building in East and Central Africa. Here is what is being built, who is paying, and why it matters to every Kenyan who contributes to NSSF.

Two tall glass towers in Nairobi
How the NSSF Twin Towers will look when finished.

The towers in numbers

260 mTower A, 60 storeys: set to be the tallest in East and Central Africa
140 mTower B, 35 storeys
KSh30bnestimated cost, fully funded by NSSF
ItemDetail
LocationJunction of Uhuru Highway and Kenyatta Avenue, Nairobi CBD
LandA 3.85-acre plot valued at about KSh4 billion, idle for years
UsesPremium offices, a business hotel, serviced apartments, shops and conference space
Viewing deckA public observation deck on the 56th floor
ParkingAbout 1,150 cars in basement and podium levels
ContractorChina Road and Bridge Corporation (CRBC), a subsidiary of CCCC
CompletionExpected late 2028 to early 2029

How tall is that, really?

Tower A would overtake every building in the region:

BuildingHeight
NSSF Tower A, Nairobi (planned)~260 m
Commercial Bank of Ethiopia HQ, Addis Ababa209 m
Britam Tower, Nairobi200 m
GTC Office Tower, Nairobi184 m
Old Mutual Tower, Nairobi163 m
Times Tower, Nairobi140 m

Heights as reported when the project was announced in February 2026.

Where is the work now?

  • NSSF unveils the project. NEMA invites public comment on its Environmental Impact Assessment.

  • Excavation begins after approvals from NEMA and the National Construction Authority.

  • Aerial photos show deep excavation almost finished, retaining walls in place and parts of the raft foundation already cast.

  • Expected completion, roughly three years of construction.

Two towers under construction with cranes
The towers rising. Work on site is currently at the foundation stage.
On site now (November 2026): new site footage shows crews pouring the raft foundation through the night, with concrete pumps working in the deep excavation. A caption from the construction team says the raft slab for Tower B, about 1,250 cubic metres of concrete, was poured in a single 15-hour session. A raft is a thick slab of steel and concrete that spreads a tower's weight across the ground.
Construction workers guiding a concrete hose at night
Night shift at the NSSF Twin Towers site: workers guide the concrete hose into the raft foundation. Site footage: Kenya Vision 2060
A concrete pump pouring into a deep excavation at night
The raft pour inside the deep excavation. Site footage: Kenya Vision 2060
Your NSSF deductions in 2026: workers and employers each pay 6% of pensionable pay. Tier I covers earnings up to KSh9,000 (max KSh540 each); Tier II covers KSh9,001–108,000 (max KSh5,940 each). Employers must remit by the 9th of the next month or pay a 5% monthly penalty, NSSF warned on 9 November.

Why NSSF is building it

  1. Make idle land pay. NSSF CEO David Koros: "That land has been idle for years and has not been giving contributors any benefit."
  2. Earn returns for members. NSSF targets a return of at least 12%, partly by selling finished units to investors.
  3. Bring life back to the CBD. "We want people to live in the city again," Koros says. Homes, a hotel and shops keep the area busy after office hours.
  4. Jobs and taxes. NSSF says construction will create direct and indirect jobs and use local materials.

Why it matters to your payslip

NSSF money comes from the deductions on every formal worker's payslip. Higher NSSF contributions in recent years have given the Fund far more cash to invest. Business Today reports NSSF expects to collect about KSh100 billion this year. Projects like the twin towers are where some of that money goes, so whether they pay off affects members' future pensions.

The questions to watch: Will the towers be finished on time and on budget? Will NSSF find enough buyers and tenants when Nairobi already has empty office space? Will the Fund publish the project's returns? NSSF has had troubled property projects before, so members are right to ask for clear reporting. We'll update this page as the towers rise.
Aerial view of Uhuru Park and Uhuru Highway in Nairobi
Uhuru Park and Uhuru Highway, the area around the site. Still from our video.

Related: Kiambu Road's KSh38bn upgrade · Nairobi rents and land prices.

Watch the videos

East & Central Africa's Future Tallest Building: NSSF Twin Towers

East & Central Africa's Tallest Building Is Coming to Nairobi

NSSF Tower vs Britam, GTC & Addis Ababa: Who's Tallest?

Your NSSF Money Is Building Nairobi's Tallest Tower: Will It Pay Off?

NSSF Twin Towers: Inside the 15-Hour Night Pour

Subscribe on YouTube

Free, every week

Get one clear explainer in your inbox

New explainers, data and videos, straight from Nairobi. No spam, unsubscribe any time.

Prefer WhatsApp?

Follow the WhatsApp Channel